Barun Sengupta metro station

Metro station in Kolkata, India From Wikipedia, the free encyclopedia

Barun Sengupta metro station

Barun Sengupta (also known as Science City), is a station of Orange Line of the Kolkata Metro located at Parama Island in the Dhapa area of Kolkata, West Bengal, India, serving Dhapa, ITC Royal Bengal, JW Marriott and Science City areas.[2][3] The station is named in honour of the founder of Bartaman, Barun Sengupta. The station is elevated above the Eastern Metropolitan Bypass.[4][5]

Quick Facts General information, Location ...
Barun Sengupta

বরুণ সেনগুপ্ত
Kolkata Metro station
General information
LocationG9VX+GPC, Dhapa, Kolkata, West Bengal 700105
Coordinates22.543986°N 88.339274°E / 22.543986; 88.339274
Owned byMetro Railway, Kolkata
Platforms2 side platforms
Tracks2
Construction
Structure typeElevated
ParkingYes
Other information
StatusUnder Construction
History
OpeningExpected to open in 2024.[1]
Electrified750 V DC third rail
Services
Preceding station Kolkata Metro Following station
Ritwik Ghatak
towards Kavi Subhash
Orange Line Beleghata
towards Jai Hind
Location
Close

Location

This station is located in Dhapa across the service road and footpath on the eastern side of Biswa Bangla Sarani at Parama Island.[6][7] The main elevated structure of the station is situated along the service road and footpath adjacent to the New Garia-bound lane of Biswa Bangla Sarani near Maa Flyover.[8] It is geographically located at 22.543986°N 88.399274°E / 22.543986; 88.399274.[9] The previous station of the station is Ritwik Ghatak metro station at a distance of 1.4 km (0.87 mi) and the next station is Beleghata metro station at a distance of 0.9 km (0.56 mi).[10][11]

History

Summarize
Perspective

This project was sanctioned in the budget of 2010–11 by Mamata Banerjee with a project deadline of six years.[12] The execution of this project has been entrusted to RVNL at a cost of Rs 3951.98 crore.[13] It will help to reduce travel time between the southern fringes of Kolkata to Netaji Subhas Chandra Bose International Airport. In October 2011, RVNL awarded Gammon India Limited, the tender for the construction of the metro corridor from VIP Bazar Metro Station to Nikko Park (Nalban metro station),[14] including stations, as part of Package-II of Orange Line. Amongst those metro stations, one in Dhapa was also sanctioned, i.e., Barun Sengupta.[15][16][12] In January 2012, the construction of the metro station along with the metro line started. The construction of the station was stopped in 2015 due to land dispute at Tagore Park culvert and a pair of footover bridges.[17] The construction of the station started again in May 2017[18][19][20][21] and was fully completed in early 2023.[22][20][23] But the metro couldn't be started due to a viaduct gap over Tagore Park culvert.[24][25]

A week later after inauguration and a day after commercial run started on Kavi Subhash-Hemanta Mukhopadhyay section, in March 2024, RVNL announced the completion of that 76 m viaduct gap after construction of a single-span hanging steel bridge over the disputed Tagore Park culvert. This completed the viaduct upto Beleghata metro station, clearing the way for commercial operations at Barun Sengupta.[26] Trial runs have started in the same month. The station is expected to be operational by late 2024.[27]

Station

Summarize
Perspective

Structure

Barun Sengupta Metro Station is an elevated metro station and has a total of 3 levels. Station entrances and exits begin or end at the first level or ground level.[28] Second-level or L1 or intermediate level houses station fare control, station agents, metro vending machines, crossovers, etc. The third level or L2 or the final level houses the platforms and rail tracks. The station is 200 meters long and 25 meters wide.[10][20][29][11]

The station has four entrances and exits. The station is being built with state-of-the-art technology. In addition to staircases, it will be equipped with lifts and escalators. The station also has drinking water and toilet facilities.[10][20][29][30]

Layout

Barun Sengupta track layout
P2
P1
Station with two tracks and two side platforms
Layout
G Street Level Exit/Entrance
L1 Mezzanine Fare control, station agent, Metro Card vending machines, crossover
L2 Side platform doors will open on the left Disabled access
Southbound Towards →Kavi Subhash→ next station is Ritwik Ghatak
Northbound Towards ←Jai Hindnext station is Beleghata
Side platform doors will open on the left Disabled access
L2

Power and signal systems

Like other stations and lines of Kolkata Metro, this station has 750 volt DC powered third rail. The electricity system will be used to operate the train.[31]

Train movement at this station will be managed by communication based train control signaling system. With this signal system, trains can be operated at intervals of 90 seconds.[32]

Services

Services have not started from this station. Currently the station is under construction and is set to be opened in 2024.[27][22]