Line 6 (Pink Line) of the Mumbai Metro is a rapid transit metro line in the city of Mumbai, Maharashtra, India. The 14.477 km (8.996 mi) elevated line will connect Lokhandwala Complex with Vikhroli and will have 13 stations.

Quick Facts Mumbai Metro Pink Line 6, Overview ...
Mumbai Metro Pink Line 6
Overview
StatusUnder construction
OwnerMMRDA
Line number6
LocaleMumbai, Maharashtra, India
Termini
Stations13
WebsiteLine 6
Service
TypeRapid transit
SystemMumbai Metro
Depot(s)Kanjurmarg
History
Planned opening2025 (2025)
Technical
Line length15.18 km (9.43 mi)
Number of tracks2
CharacterElevated
Track gauge1,435 mm (4 ft 8+12 in) standard gauge
Highest elevation38 m (125 ft)
Line 6 map

Line 6
Kanjurmarg Depot
0.000
Vikhroli EEH
Central line Kalyan and CSMT
0.9736
Kanjurmarg (West)
Gandhi Nagar (Kanjurmarg) on Line 4
2.6316
IIT Powai
3.6960
Powai Lake
4.5453
Rambaug (Powai)
5.5576
Saki Vihar Road
Aarey Colony on Line 3
Aarey Colony Ramp
SEEPZ on Line 3
6.6939
SEEPZ Village
7.8168
Mahakali Caves
9.3646
Shyam Nagar
10.3265
Jogeshwari East on Line 7
Western line Dahanu Road and Churchgate
11.4863
Jogeshwari (West)
12.4754
Adarsh Nagar
Lower Oshiwara on Line 2
13.2042
Swami Samarth Nagar (Lokhandwala)
Close

Line 6 will also provide interchanges with Yellow Line 2 at Adarsh Nagar, with Aqua Line 3 at SEEPZ, with Green Line 4 at Kanjurmarg West, and with Red Line 7 at Jogeshwari Vikhroli Link Road. It also offers connectivity with the Mumbai Suburban Railway's Western line at Jogeshwari and with the Central line at Kanjurmarg.

Line 6 is expected to open by 2025.

Planning

Summarize
Perspective

A 19.5 km (12.12 mi) metro line connecting Bandra Kurla Complex with Kanjurmarg via the airport was proposed as Line 6 in the original Mumbai Metro master plan unveiled by the Mumbai Metropolitan Region Development Authority (MMRDA) in 2004.[1] In June 2015, the MMRDA proposed building a 12 km (7.46 mi) metro line from JVLR to Kanjurmarg as part of a plan to build 6 new metro lines at a total estimated cost of 64,000 crore (US$7.5 billion).[2] On 19 October 2016, the Mumbai Metropolitan Region Development Authority (MMRDA), headed by Chief Minister Devendra Fadnavis, approved a plan to build a 14.47 km (8.99 mi) metro rail line connecting Lokhandwala Complex in Andheri to Vikhroli and Kanjurmarg in the east. The line would have 13 stations and was estimated to cost 6,672 crore (US$780 million).[3] The detailed project report for Line 6 was prepared by the Delhi Metro Rail Corporation (DMRC) in December 2016.[4] The project was approved by the Maharashtra Cabinet on 24 October 2017.[5]

The MMRDA issued a tender to conduct a detailed aerial mapping survey of the alignment in April 2017. Authorities were to determine the location of trees along the alignment with an accuracy of up to 10 cm (3.9 in), utilizing a differential GPS (DGPS), while a digital aerial triangulation system is to help determine the types of trees, their heights and diameters.[6] The project received Coastal Regulation Zone (CRZ) clearance from the Maharashtra Coastal Zone Management Authority (MCZMA) in June 2017. A 1.1 km (0.68 mi) stretch of Line 6 passes through CRZ areas at the junction of the JVLR and the Eastern Express Highway near Nehru Nagar.[7] The MMRDA utilized a drone to carry out survey work for Line 6. The drones were fitted with 360 degrees camera that provide up to 3 millimetres (0.12 in) accuracy. The aerial survey takes less time than a regular survey, achieves greater accuracy and helps protect against false claims for compensation.[8]

In November 2017, the MMRDA stated that it had reached an agreement with the Brihanmumbai Municipal Corporation (BMC) to build a 2 km (1.24 mi) section of Line 6 on a common pier with a flyover. The BMC had been planning to build a flyover connecting Jogeshwari West and the Jogeshwari Vikhroli Link Road (JVLR) along the same alignment of Line 6. Per the agreement, the metro piers and viaduct would be constructed first and the flyover would be built below it. Line 6 forms the top deck of a three deck structure on this 2 km (1.24 mi) stretch as the flyover itself passes over an existing rail overbridge.[9]

In April 2018, the BMC stated that it was putting work on a proposed crocodile park at Powai Lake on hold until Line 6 was completed.[10] The MMRDA faced criticism from Lokhandwala and Powai residents at a public consultation meeting held on 21 May 2019.[11]

Alignment

The fully elevated line is 14.477 km (8.996 mi) long with 13 stations. The line begins at Swami Samarth Nagar station in Lokhandwala Complex and passes over Line 2A's viaduct near Infinity Mall junction on Link Road at a height of 20 metres (66 ft). Line 6 continues east passing over railway lines at Jogeshwari, Line 7's viaduct at the Western Express Highway, and the JVLR. It continues along the periphery of Powai Lake and terminates at Vikhroli station on the Eastern Express Highway. Line 6 has a total of 50 curves along the route, including many sharp turns. The detailed project report noted that the ground along the alignment was "undulated" resulting in a gradient that was very steep.[12]

Line 6 is the highest metro line in India. The average height of the pillars supporting the line is 16 metres (52 ft) (fourth highest in India), but passes at heights over 30 metres (98 ft) in some sections. The tallest pillar on Line 6 is located at Gandhi Nagar in Kanjurmarg. It is 38 metres (125 ft) in height and is the tallest metro pillar in India.[13] The tallest station on the line is Kanjurmarg at height of 30 metres (98 ft) above ground level.[14]

Bidding

More information Civil Work, Package ...
Civil Work
Package Section Length Successful bid/cost Contractor Award
BC-01R1 Vikhroli EEH – Powai Lake 4.772 km (2.965 mi) 444.98 crore (US$52 million) J Kumar – CRTG 13 Feb 2019
BC-02R Powai Lake – Mahakali Caves 4.329 km (2.690 mi) 372.22 crore (US$43 million) MBZ-EIIL 05 Sept 2018
BC-03 Mahakali Caves – Swami Samarth Nagar 6.079 km (3.777 mi) 867.75 crore (US$100 million) J Kumar – CRTG 07 Aug 2018
Total 15.18 km (9.43 mi) 1,684.95 crore (US$200 million)
Architectural Finishing Works
Package Section Length Successful bid/cost Contractor Award
CA-264 IIT Powai to Vikhroli EEH 76.68 crore (US$9.0 million) SS Constructions 1 Jan 2025
CA-265 Mahakali Caves to Powai lake 124.41 crore (US$15 million) NA Construction 8 Jan 2025
CA-266 Swami Samarth Naga to Shyam Nagar 165.93 crore (US$19 million) Landmark – Neev JV 8 Jan 2025
Total 366.94 crore (US$43 million)
Miscellaneous
Package Contract Successful bid/cost Contractor Award
MT-08 Track Fastening 29.84 crore (US$3.5 million) Pandrol Rahee 11 May 2021
MT-09R Track Work 80.49 crore (US$9.4 million) Paras Railtech 29 Jan 2024
CA-208 Kanjurmarg Depot Consultant 20.42 crore (US$2.4 million) CEG – KNR 1 Apr 2024
CA-209 Kanjurmarg Depot Construction 547.45 crore (US$64 million) Sam India 12 Mar 2024
CA-232 Rolling Stock, Platform Screen Door & Signaling Contract Bidding Underway
CA-233 Power Supply and Traction, E&M, Lifts & Escalators To Be Confirmed IRCON To Be Confirmed
CA-238 Automatic Fare Collection system Bidding Underway
Total 678.2 crore (US$79 million)
Total Cost 2,730.09 crore (US$320 million)
Close

Construction

Summarize
Perspective

The DMRC was appointed as the implementing agency for the project by the MMRDA in November 2017. The DMRC invited bids for the construction of Line 6 on 28 November 2017. The work was split into 3 packages. The first package included the IIT Powai, Kanjurmarg West and Vikhroli (EEH) stations.[15][16] The second package included the section from Lokhandwala to Mahakali Caves.[17] Construction of the first two packages required the cutting 899 trees.[11] The DMRC awarded J Kumar Infraprojects an 867 crore (US$100 million) contract for the second package from Lokhandwala to Mahakali Caves in August 2018.[17][18]

Girder launching began in November 2020. The MMRDA stated in the same month that around 21% of the total work had been completed.[19] A 29.5-metre tall straddle carrier was used to launch girders for the line.[13] A crane at a construction site along the JVLR near Kanjurmarg toppled and collapsed while installing a concrete girder on 16 January 2022, resulting in the death of the crane operator.[20] About half the work on the line had been completed by July 2022,[14] and 65% of civil works had been completed by December 2022.[21] On 6 July 2023, the MMRDA stated that it had completed building 657 out of 768 pillars (70.75%) required for Line 6.[22]

Stations

Summarize
Perspective

The line will consist of 13 stations from Swami Samarth Nagar in Lokhandwala Complex in Andheri (West) to Vikhroli (East). It will have interchanges with Lines 2, 3, 4 and 7.[23] Stations on the line will be equipped with platform screen doors.[24]

More information Pink Line 6, # ...
Pink Line 6
# Station Name Opening[25] Interstation Distance Connections Layout
EnglishMarathi
1Swami Samarth Nagar (Lokhandwala)स्वामी समर्थ नगर (लोखंडवाला)December 20260 km (0 mi)NoneElevated
2Adarsh Nagarआदर्श नगरDecember 20260.7288 km (0.4529 mi)Line 2Elevated
3Jogeshwari (West)जोगेश्वरी (पश्चिम)December 20260.9891 km (0.6146 mi)Jogeshwari railway station,
Western Line (Mumbai Suburban Railway)
Elevated
4JVLR Junctionजेवीएलआर जंक्शनDecember 20261.598 km (0.993 mi)Line 7Elevated
5Shyam Nagarश्याम नगरDecember 20260.9619 km (0.5977 mi)NoneElevated
6Mahakali Cavesमहाकाली लेणीDecember 20261.5478 km (0.9618 mi)NoneElevated
7SEEPZ Villageसीप्झ गावDecember 20261.1228 km (0.6977 mi)Line 3Elevated
8Saki Vihar Roadसाकी विहार रोडDecember 20261.1363 km (0.7061 mi)NoneElevated
9Rambaug (Powai)रामबाग (पवई)December 20261.0122 km (0.6290 mi)NoneElevated
10Powai Lakeपवई तलावDecember 20260.8493 km (0.5277 mi)NoneElevated
11IIT Powaiआयआयटी पवईDecember 20261.0644 km (0.6614 mi)NoneElevated
12Kanjurmarg (West)कांजूरमार्ग (पश्चिम)December 20261.658 km (1.030 mi)Line 4 (Under Construction),
Kanjurmarg railway station,
Central Line (Mumbai Suburban Railway)
Elevated
13Vikhroli EEHविक्रोळी इइएचDecember 20261.056 km (0.656 mi)NoneElevated
Close

Infrastructure

Rolling stock

The MMRDA floated tenders to procure 108 metro cars for Line 6 in June 2023.[26]

Depot

The depot for Line 6 is proposed to be located at Kanjurmarg.[27]