Orange Line (Namma Metro)

Proposed line of Bengaluru's Namma Metro From Wikipedia, the free encyclopedia

The Orange Line or ORR-West Line is an upcoming metro line serving Bangalore as part of the Namma Metro network in the city. This metro line will serve the industrial areas[a], manufacturing units[b], educational institutions[c], providing connectivity to the southern part of the city[d], thereby improving last-mile connectivity to commercial centres, industrial hubs, educational institutions, and healthcare facilities.[1][2] The line was approved by the Union Cabinet on August 17th, 2024 and is scheduled for completion in 2029. [3][4][5][6][7][8]

Quick Facts Overview, Other name(s) ...
Orange Line
Overview
Other name(s)ORR-West Line
StatusApproved
OwnerBangalore Metro Rail Corporation Limited (BMRCL)
LocaleBangalore, Karnataka, India
Termini
  • Kempapura
  • JP Nagar 4th Phase
Connecting linesOperational (2):
Purple Line Green Line
Upcoming (3):
Pink Line Blue Line Red Line
Stations22 (Corridor-I) + 11 (Corridor-II)
Websitebmrc.co.in
Service
TypeMetro
SystemNamma Metro
Depot(s)Magadi Road (TBD)
History
Planned opening2029; 4 years' time (2029)
Technical
Line length42 km (26 mi)
Number of tracks2
CharacterElevated (TBD)
Track gauge1,435 mm (4 ft 8+12 in) standard gauge
Electrification750 V DC third rail
Orange Line Map (TBC)

Blue Line to Krishnarajapura
or Central Silk Board
Blue Line Kempapura
Blue Line Under construction
Blue Line
Red Line
Hebbala
(Red Line - Proposed)
Blue Line towards KIAL Terminals
Red Line towards Sarjapura
Nagashetty Halli
BEL Circle
Muthyalanagar
Indian Railways Towards
Tumakuru and Yesvantpur Jn
Green Line Peenya
Kanteerava Nagar
Hosahalli
Freedom Fighter's Colony
KHB Layout
Prem Nagar
Kamakshi Palya
Sumanahalli Cross
Anjana Nagar
Nagarbhavi BDA Complex
Sunkadakatte Depot (U/C)
Papireddy Palya
Herohalli
Vinayaka Layout
Byadarahalli
Nagarbhavi Circle
Indian Railways Towards
Kengeri and KSR Bengaluru
Kamath Layout
Mysuru Road
Kadabagere
Dwaraka Nagar
Hosakerehalli
Kamakhya Bus Depot
Kadirenahalli
Jaya Prakash Nagar
JP Nagar 5th Phase
JP Nagar 4th Phase
Pink Line
Under construction
Legend:
Kempapura ⇔ JP Nagar Phase 4 (Corridor-1)
Sri Balagangadharanatha Swamiji Stn., Hosahalli ⇔ Kadabagere (Corridor-2)
Close

History

Summarize
Perspective

BMRCL began planning Namma Metro Phase-III in 2013, shortly after announcing Phase-II, which included the Yellow Line and Pink Line. Later in June 2013 BMRCL partnered with RITED Limited to conduct a pre-feasibility study for each proposed corridor

By 2016, BMRCL submitted its Phase-III proposal to the Ministry of Urban Development, which initially spanned 150.94km. However, following the feasibility the network size was reduced to 102km, with the remaining corridors being planned for Light Rail. The proposed lines were

  • Nagavara - Kempegowda International Airport
  • Carmelaram - Yelahanka
  • Marathahalli - Hosakerehalli
  • Silkboard - Hebbal via KR Puram.

However, in 2017 the Karnataka Government announced that the Silkboard - Hebbal line and the Nagavara - Airport line were merged to create the Blue Line and fast tracked to Phase 2A and Phase 2B.

In 2018 the Karnataka Government officially confirmed Phase III with several modifications. Multiple new lines were introduced while some others were dropped. Following another round of modifications in 2020, only two lines were finalized to be part of Phase-III

  • Magadi Road Toll Gate to Kadabagere line
  • JP Nagar to Kempapura

In July 2020, RITES Limited was assigned to prepare the Detailed Project Report (DPR) work for Phase-III. RITES submitted the DPR to the State Government who approved it in November 2022. The final approval was received from the Central Government in August 2024 paving the way for BMRCL to start land acquisition and tender notification.

Tendering

Summarize
Perspective

As of January 2025 BMRCL has issued tenders for Geotechnical Investigations and Detailed Design Consultancy (DDC). Once the Geotechnical Investigations are finished and finalized with the DDC BMRCL plans to release the Civil Work Tender.

More information Pre-Construction Activity, Tendering ...
Pre-Construction Activity
Tendering Section Activity Successful Bid /Cost Contractor Award
Phase-3/GTI/2024/109/ Pkg-1 JP Nagar 4th Phase to Mysore Road Geotechnical Investiation 1.32 crore (US$150,000) Manglam Consultancy 23 Jul 2024
Phase-3/GTI/2024/109/ Pkg-2 Mysore Road to Kanteerava Studio Geotechnical Investiation 1.31 crore (US$150,000) SECON 23 Jul 2024
Phase-3/GTI/2024/109/ Pkg-3 Kanteerava Studio to Kempapura Geotechnical Investiation 1.32 crore (US$150,000) Myrtle Project 23 Jul 2024
Phase-3/GTI/2024/109/ Pkg-4 Hosahalli to Kadabagere Geotechnical Investiation 1.54 crore (US$180,000) SECON 23 Jul 2024
Phase-3/DDC1/RFP/2024/115 JP Nagar 4th Phase to BDA Complex Nagarbhavi Detailed Design Consultant Bidding Underway
Phase-3/DDC2/RFP/2024/116 Sumanahalli Cross to Kempapura Detailed Design Consultant Bidding Underway
Phase-3/DDC3/RFP/2024/117 Hosahalli Station to Kadabagere Detailed Design Consultant Bidding Underway
EPDD-5 Traction and Power Supply Detailed Design Consultant Bidding Underway
Total 5.49 crore (US$630,000)
Close

Funding

As per the initial Detailed Project Report (DPR) line is estimated to cost Rs.15,611 crores. The cost includes the construction of both new metro lines along with flyovers, which will be built along the metro pillars. The funding is at the moment planned at

  • Government of Karnataka (Equity): Rs.2,037 crores
  • Government of India (Equity): Rs.2,037 crores
  • Government of Karnataka Subordinated debt for land & RR: Rs. 2019 crores
  • GOK Subordinated debt for central taxes: Rs. 489 crores
  • GOI Subordinated debt for central taxes: Rs. 489 crores
  • External Debt: Rs. 7577 crores

Stations

Summarize
Perspective

ORR-West Line (Orange Line)

Interchanges

Passenger interchange facilities, connecting to other metro and railway lines, are proposed at the following station

More information #, Station Name ...
Orange Line
# Station Name Connections Station Layout
EnglishKannada
1 Kempapura ಕೆಂಪಾಪುರ Blue Line (Under Construction) Elevated
2 Hebbala ಹೆಬ್ಬಾಳ Blue Line (Under Construction)

Red Line (Approved)

 Mallige  (Under Construction)

Elevated
3 Patelappa Layout ಪಟೇಲಪ್ಪ ಬಡಾವಣೆ Elevated
4 BEL Circle ಬಿ ಇ ಎಲ್ ವೃತ್ತ Elevated
5 Bahubhali Nagara ಬಾಹುಬಲಿ ನಗರ Elevated
6 Peenya ಪೀಣ್ಯ Green Line Elevated
7 Kanteerava Studio ಕಂಠೀರವ ಸ್ಟುಡಿಯೋ Elevated
8 Freedom Fighters Cross ಫ್ರೀಡಂ ಫೈಟರ್ಸ್ ಕ್ರಾಸ್ Elevated
9 Chowdeshwari Nagara ಚೌಡೇಶ್ವರಿ ನಗರ Elevated
10 Sumanahalli Cross ಸುಮನಹಳ್ಳಿ ಕ್ರಾಸ್ Grey Line (Approved) Elevated
11 Nagarbhavi BDA Complex ನಾಗರಬಾವಿ ಬಿ ಡಿ ಎ ಸಂಕೀರ್ಣ Elevated
12 Dr. Ambedkar Institute of Technology ಡಾ|| ಅಂಬೇಡ್ಕರ್‌ ತಾಂತ್ರಿಕ ಮಹಾವಿದ್ಯಾಲಯ Elevated
13 Vinayaka Layout ವಿನಾಯಕ ಬಡಾವಣೆ Elevated
14 Nagarabhavi Circle ನಾಗರಬಾವಿ ವೃತ್ತ Elevated
15 Mysuru Road ಮೈಸೂರು ರಸ್ತೆ Purple Line Elevated
16 PES University ಪಿಇಎಸ್ ವಿಶ್ವವಿದ್ಯಾಲಯ Elevated
17 Hosakerahalli Cross ಹೊಸಕೆರೆಹಳ್ಳಿ ಕ್ರಾಸ್ Elevated
18 Kamakya Bus Depot ಕಾಮಾಕ್ಯ ಬಸ್‌ ಘಟಕ Bus interchange Kamakya Bus Depot Elevated
19 Kadirenahalli Cross ಕದಿರೇನಹಳ್ಳಿ ಕ್ರಾಸ್ Elevated
20 Jaya Prakash Nagar ಜಯಪ್ರಕಾಶ ನಗರ Green Line Elevated
21 JP Nagar 5th Phase ಜೆಪಿ ನಗರ ೫ನೇ ಹಂತ Elevated
22 JP Nagar 4th Phase ಜೆಪಿ ನಗರ ೪ನೇ ಹಂತ Pink Line (Under Construction) Elevated
Close

Hosahalli-Kadabagere Line (Grey Line)

Interchanges

Passenger interchange facilities, connecting to other metro and railway lines, are proposed at the following stations:

More information Hosahalli-Kadabagere Line, # ...
Hosahalli-Kadabagere Line
# Station Name Connections Station Layout
EnglishKannada
1 Hosahalli ಹೊಸಹಳ್ಳಿ Purple Line Elevated
2 K H B Colony ಕೆ ಎಚ್ ಬಿ ಕಾಲೋನಿ Elevated
3 Vinayaka Nagara ವಿನಾಯಕ ನಗರ Elevated
4 Sumanahalli Cross ಸುಮನಹಳ್ಳಿ ಕ್ರಾಸ್ Orange Line Elevated
5 Sunkadakatte ಸುಂಕದಕಟ್ಟೆ Elevated
6 Herohalli ಹೇರೋಹಳ್ಳಿ Elevated
7 Byadarahalli ಬ್ಯಾಡರಹಳ್ಳಿ Elevated
8 Forest Gate ಅರಣ್ಯ ದ್ವಾರ Elevated
9 Kadabagere ಕಡಬಗೆರೆ Elevated
Close

Integration of the key areas of the city

These are the notable areas that will be integrated as part of the Phase 3 of Namma Metro and they are as given below:-

  1. Peenya Industrial Area, IT Industries on Bannerghatta Main Road
  2. Engineering and Textile Manufacturing Units on Tumkur Road, Bharat Electronics Limited (BEL)
  3. PES University, Ambedkar College, Polytechnic College, KLE College, Dayananda Sagar University
  4. Outer Ring Road West Side, Magadi Road with its neighbouring areas

See also

References

Loading related searches...

Wikiwand - on

Seamless Wikipedia browsing. On steroids.