The Northern Link is a proposed rapid transit line of the MTR[1] system of Hong Kong which would connect the Tuen Ma line and the Lok Ma Chau Spur Line of the East Rail line. The link would also serve as a connection to the border checkpoint to mainland China for passengers to and from the western New Territories.[2] The Northern Link would start at Kam Sheung Road and end at Kwu Tung, with 3 intermediate stations.

Quick Facts Northern Link 北環綫, Overview ...
Northern Link
北環綫
Overview
Other name(s)NOL
Status
  • Phase 1: Under construction
  • Phase 2: Construction expected to begin 2025
OwnerKowloon-Canton Railway Corporation
LocaleDistricts: Yuen Long
Termini
Stations5
Service
SystemMTR
Operator(s)MTR Corporation
History
Planned opening
  • Phase 1: 2027; 3 years' time (2027)
  • Phase 2: 2034; 10 years' time (2034)
Technical
Line length26 km (16 mi)
Track gauge1,435 mm (4 ft 8+12 in) standard gauge
Route map

Kwu Tung     
proposed extension
proposed spur line to Huanggang Port
San Tin
Ngau Tam Mei
Au Tau
Kam Sheung Road     
Pat Heung Depot
Close
Quick Facts Traditional Chinese, Simplified Chinese ...
Northern Link
Traditional Chinese北環綫
Simplified Chinese北环线
Transcriptions
Standard Mandarin
Hanyu PinyinBěi Huán Xiàn
Close

Other benefits for constructing this project are significantly shorter journey times for certain trips (for example, the Yuen Long to Fanling route would be reduced in length from 20 stations to 5), significantly reducing costs for these trips, as well as relieving the large number of passengers using the East Rail line by diverting some passengers to the Tuen Ma line.

History

According to the Railway Development Strategy 2014, a shuttle service between Kam Sheung Road station and Kwu Tung station spanning 10.7 km (6.6 mi) was expected to begin construction in 2018 and be inaugurated in 2023.[3]

The initial line is expected to cost HK$62 billion in December 2015 prices, with an average of HK$500 million/km.[4][5]

Thumb
Development of Northern Link as mentioned in the 2021 Policy Address, which a spur line and an extension would be built (outdated)

Phases

The Northern Link (NOL) project is expected to consist of four phases.

Phase 1

Phase 1 consists of the construction and completion of Kwu Tung station that will initially serve the East Rail line after its opening, then later the Northern Link after the completion of Phase 2. It had been partially built by KCR Corporation during the construction of the Lok Ma Chau Spur Line. Construction of Kwu Tung station was approved by the government in 2022 is scheduled to commence in 2023 with completion due in 2027.[6] Construction started on September 29, 2023.[7]

The station was expected to cost HK$3.5 billion as of December 2015.[8][9] As of July 2023, the estimated cost had risen to HK$5.9 billion.[10]

Phase 2

Phase 2 consists of the building of the 10.7 km main line from Kam Sheung Road station to Kwu Tung station. It also includes the construction of 3 new stations (Au Tau, Ngau Tam Mei and San Tin) along with the expansion of Kam Sheung Road station to accommodate the new tracks and platforms. Planning and designing began in 2021. Construction of the mainline is planned to begin in 2025 and be completed in 2034.[11]

It is expected to cost HK$58.5 billion in December 2015 prices.[12][13]

The 5.8 km Northern Link Spur Line starts from San Tin station and connects to San Tin Technopole, Hong Kong-Shenzhen Innovation and Technology Park before terminating at the Huanggang Port in Shenzhen. Planning and design for the line is expected to start in 2024.[14]

The 9.5 km eastern extension extends eastward from Kwu Tung to Ping Che via Lo Wu South and Man Kam To.[14] Originally planned as part of the extension, the section from Heung Yuen Wai to Fanling station will form the new 8.5 km Northeast New Territories Line.[15]

Stations

More information Station Name, Connections ...
Station Name Connections Opening date District
English Chinese
Phase 1
(Under construction)
Kwu Tung 古洞      East Rail line 2027 North
Phase 2
Kam Sheung Road 錦上路      Tuen Ma line 20 December 2003 Yuen Long
Au Tau 凹頭 2034
Ngau Tam Mei 牛潭尾
San Tin 新田
Eastern Extension
Lo Wu South 羅湖南      East Rail line TBA North
Man Kam To 文錦渡
  • Through Border Checkpoint:
  • Shenzhen Metro Wenjin: 9
Ping Che 坪輋
Northern Link Spur Line
San Tin 新田 2034 North
Chau Tau 洲頭 TBA
Lok Ma Chau Loop 落馬洲河套
Huanggang Port 皇崗口岸
Close

Controversies

Land hoarding

In July 2021, Liber Research Community found that developers had begun to hoard land alongside the Northern Link line, buying at least 80 hectares of land near the line.[16]

References

Wikiwand in your browser!

Seamless Wikipedia browsing. On steroids.

Every time you click a link to Wikipedia, Wiktionary or Wikiquote in your browser's search results, it will show the modern Wikiwand interface.

Wikiwand extension is a five stars, simple, with minimum permission required to keep your browsing private, safe and transparent.