From Wikipedia, the free encyclopedia
A hammock activity (also hammock task) is a schedule or project planning term for a grouping of tasks that "hang" between two end dates it is tied to.[1][2][3][4]
A hammock activity can group tasks that are not related in the hierarchical sense of a Work Breakdown Structure, or are not related in a logical sense of a task dependency, where one task must wait for another.[5]
Usage includes:
The duration of the hammock activity (the size of the hammock) may also be set by the subtasks within it, so that the abstract grouping has a start date of the earliest of any of the subtasks and the finish date is the latest of any of the contents.
A hammock activity is regarded as a form of Summary activity[6] that is similar to a Level of Effort (LOE) activity.[7][8] Use of hammock activities is also a way to simplify the difficulties of performing Work Breakdown Structure decomposition to low levels.[9] Also, hammock tasks can represent any group of tasks in the Integrated Master Schedule (IMS) regardless of their physical location or parent Work Breakdown Structure (WBS) element.[10]
Seamless Wikipedia browsing. On steroids.
Every time you click a link to Wikipedia, Wiktionary or Wikiquote in your browser's search results, it will show the modern Wikiwand interface.
Wikiwand extension is a five stars, simple, with minimum permission required to keep your browsing private, safe and transparent.