Gorakhpur Nuclear Power Plant

Nuclear power station in Haryana, India From Wikipedia, the free encyclopedia

Gorakhpur Nuclear Power Plantmap

The Gorakhpur Nuclear Power Plant or the Gorakhpur Haryana Anu Vidyut Pariyojana (GHAVP) is a proposed nuclear power plant to be built on a 560 hectares (1,400 acres) area west of Gorakhpur village of Fatehabad district of Haryana.[1][2]

Quick Facts Official name, Country ...
Gorakhpur Nuclear Power Plant
Thumb
Location of Gorakhpur Nuclear Power Plant in Haryana
Official nameGorakhpur Haryana Anu Vidyut Pariyojana
CountryIndia
LocationGorakhpur village, Fatehabad district, Haryana
Coordinates29°26′29″N 75°37′56″E
StatusUnder Construction
Construction beganUnit 1 & 2: January 2018
Commission dateUnit 1 & 2: 2028 and 2029 respectively(planned)
Construction cost20,594 crore (equivalent to 330 billion or US$3.84 billion in 2023)
OwnerNPCIL
OperatorNPCIL
Nuclear power station
Reactor typeIPHWR-700
Reactor supplierNPCIL/BARC
Cooling sourceBhakra Main Line Canal (via Nangal hydel Channel from Bhakra Nangal Dam)
Power generation
Units under const.4 x 700 MW
External links
CommonsRelated media on Commons
Close
Thumb
The Prime Minister, Dr. Manmohan Singh addressing at the foundation stone laying ceremony of the Gorakhpur Haryana Anu Vidyut Pariyojana (Nuclear Power Project), in Fatehabad, Haryana on January 13, 2014. The Governor of Haryana, Shri Jagannath Pahadia, the Chief Minister of Haryana, Shri Bhupinder Singh Hooda and the Union Minister for Social Justice & Empowerment, Kumari Selja are also seen.

The foundation stone of the 2800 megawatt nuclear power plant was laid on 13 January 2014, however actual construction began in 2018. The first phase of the project will have an installed capacity of 1400 MW and was expected to be completed by 2025,[3] however the deadline has been now extended to 2029.[4] The construction of second phase will gather pace afterwards, which will double the capacity to 2800 MW and has a deadline of 2036.

History

Summarize
Perspective

One year after laying the foundation stone, there was no reactor construction activity. NPCIL carried out only certain pre-project activities on the land. There were problems with the Environment Court at Kurukshetra and over the possession of 28 acres, as owners of the land refused to accept compensation and to vacate the land. Officials said that the government was suffering a financial loss of Rs 7 to 8 crore per day for the delay of the project.[5]

On May 27, 2015, a police force evicted farmers living on a piece of land acquired by the NPCIL. Houses were razed, crops destroyed, and the farmers belongings and cattle carted away. In 2012, NPCIL acquired over 1,503 acres (608 ha) of land in Gorakhpur, Kajal Heri and Badopal for the setting up of nuclear power plant. The corporation had taken possession of the major part of land, but farmers owning 28 acres had refused the compensation and were not vacating the land.[6]

In March 2016, still only preparatory activities were made.[7] By 2018, NPCIL had started the procurement activities for this project, as BHEL secured the order for supply of steam generators to this project.[8]


As of April 2022, the foundation piles have been completed for units 1 and 2, while the excavation work for other structures such as cooling towers are in progress. Only pre-project activities had been carried out for units 3 and 4.[4]

Design and specification

The proposed 700 MW IPHWR-700 pressurized heavy water reactors are indigenous and similar to the ones currently under construction in Kakrapar Atomic Power Station (KAPP-3 &4) and Rajasthan Atomic Power Station (RAPP-7 & 8). Also, the reactor size and the design features of 700 MW are similar to that of 540 MWe of Tarapur Atomic Power Station 3 & 4 Units, except that partial boiling of the coolant is up to about 3% (nominal) at the coolant channel exit has been allowed.[1]

Cost and economics

Being built by the Nuclear Power Corporation of India, the project is estimated to cost 20,594 crore (equivalent to 330 billion or US$3.84 billion in 2023) as of January 2014.[1]

Units

More information Phase, Unit No. ...
Phase Unit
No.
Reactor Status Capacity in MWe Construction start First criticality Grid Connection Commercial operation Closure Notes
TypeModelNetGross
I 1 PHWRIPHWR-700 Under construction 630 700 2018 2028 (planned) [9]
2 PHWRIPHWR-700 Under construction 630 700 2018 2029 (planned) [9]
II 3 PHWRIPHWR-700 Under construction 630 700 2020 [9]
4 PHWRIPHWR-700 Under construction 630 700 2020 [9]
Close

Updates

  • (Mar 2021) First end-shield for pressurized heavy water reactor delivered.
  • (July 2021) Godrej & Boyce gets ₹468 Cr order to supply generators for PHWR project[10]
  • (July 2021) BHEL awarded steam generator contract for domestic PHWRs[11]
  • (Aug 2021) L&T delivers second end-shield for pressurized heavy water reactor [12]
  • (Sep 2021) BHEL wins order for turbine islands

See also

References

Loading related searches...

Wikiwand - on

Seamless Wikipedia browsing. On steroids.