Bulfinch Crossing (also known as the Government Center Garage Redevelopment) is a redevelopment project currently under construction in Downtown Boston, Massachusetts, United States. It will consist of two skyscrapers, a smaller residential tower, a low-rise office building, a hotel, and a low-rise retail building. Site preparation began in late 2015, and construction officially commenced on January 24, 2017. Construction on the residential tower completed in 2020.[4] The high-rise office tower, One Congress, commenced construction in 2019 and topped off in July 2021; after an announced plan to open in 2022,[5] it officially opened in September 2023.[6]
![]() | This article needs to be updated. (March 2022) |
Bulfinch Crossing | |
---|---|
One Congress | |
![]() | |
General information | |
Status | Under construction |
Type | Office, retail |
Coordinates | 42°21′46″N 71°03′31″W |
Named for | Bulfinch Triangle |
Groundbreaking | Summer 2019 |
Construction started | Late 2015 |
Completed | 2023 |
Opening | 2023 |
Height | |
Roof | 520 ft (160 m) |
Top floor | 600 ft (180 m) |
Technical details | |
Floor count | 43 |
Floor area | 1,012,000 sq ft (94,000 m2) |
Design and construction | |
Architect(s) | César Pelli |
Architecture firm | Pelli Clarke Pelli |
Developer | HYM Investment Group |
Other designers | CBT Architects |
Main contractor | Tishman Construction |
Other information | |
Facilities | MBTA subway and bus station, Bluebikes dock, charging station, Zipcar, Maven, Enterprise Rent-A-Car |
Parking | 1,160 spaces |
Website | |
bulfinchcrossing www | |
References | |
[1][2] |
Bulfinch Crossing | |
---|---|
The Sudbury | |
![]() | |
General information | |
Status | Completed |
Type | Residential, retail |
Named for | Bulfinch Triangle |
Groundbreaking | January 24, 2017 |
Construction started | Late 2015 |
Completed | 2020 |
Opening | 2020 |
Height | |
Roof | 519 ft (158 m) |
Technical details | |
Floor count | 45 |
Floor area | 547,900 sq ft (50,900 m2) |
Design and construction | |
Architect(s) | Pelli Clarke Pelli and CBT Architects |
Developer | HYM Investment Group |
Other designers | CBT Architects |
Other information | |
Number of rooms | 423 (residential), 200 (hotel) |
Facilities | MBTA subway and bus station, Bluebikes dock, charging station, Zipcar, Maven, Enterprise Rent-A-Car |
Parking | 1,160 spaces |
Website | |
bulfinchcrossing | |
References | |
[1][2][3] |
One Congress
Summarize
Perspective

The primary anchor of the Bulfinch Crossing development is One Congress, the 43-story office tower, which was completed in 2023[7]. It was designed by renowned firms Pelli Clarke & Partners and CBT Architects[8]. The building features a three-story lobby and high-end amenities.[9]
The first floor of the building contains the triple-height lobby and a restaurant, as well as a coffee bar, lounge area, and collaborative workspaces. The first four floors measure 23,200 square feet. Floors five through ten contain offices and parking, and each floor will measures 8,800 square feet. The remaining floors contain offices, and each floor measures 27,500 square feet.
The 11th floor of the building is an amenity center for office tenants. The amenities include a fitness center, basketball court, rooftop garden, a 15,000 square foot outdoor terrace and several conference roomsand a conference facility. On-site parking is also available.[10][9][11]
The building earned a platinum level of certification through the US Green Building Council's Leadership in Energy and Environmental Design certification program, and also has a 2-Star Fitwel certification.[11]
In the summer of 2018, developers of One Congress & Bulfinch Crossing announced on Bulfinch Crossing's Twitter that construction on One Congress would begin in summer of 2019 and also announced that it will be opening in 2022.[12] Ultimately, the building delivered in 2023[13]. In January 2019, State Street Corporation was announced to be the anchor tenant in the new building,[14] and in September 2023 they began operations from the location as their new global headquarters.[15] Other tenants include InterSystems and K&L Gates.[16]
Residential tower
The second largest building in the development is the larger residential tower (sometimes called Residential Tower I by the developer), which is planned to be at least 480 ft (150 m) tall.
The tower was originally planned to consist of 486 apartments, but will now instead contain only 368 apartments and 55 condos. This change was announced in July 2017 when the developer decided to convert 118 apartments into 55 condos due to a slowing demand for luxury housing in Boston.[3]
The residential tower will contain a fitness center, swimming pool, rooftop garden, clubroom, private kitchen and diner, yoga room, golf simulator, pet spa, concierge services and a sky lounge and terrace. On-site parking is also available.[9][17]
Other buildings
Summarize
Perspective
Along with the two main towers of the development, four smaller buildings and a public square will be constructed. Along with these buildings, there will be nearly 4,132,500 sq ft (383,900 m2) in the entire development.
Residential Tower II
A smaller residential tower (officially named Residential Tower II), is being constructed alongside the rest of the development. It is planned to rise at least 299 feet (91 metres) and contain 28 stories. The tower is planned to be primarily residential, with 291 units. At least 8,400 sq ft (800 m2) of the building will be designated for retail use.[9]
Boutique Office
In addition to the main office tower, a smaller office building (officially named Boutique Office) is under construction; it is planned to contain at least 163,800 sq ft (15,200 m2) of both office and retail space. The building will rise 152 feet (46 meters) and will contain 11 stories. It is planned to have a private terrace for office workers.[9]
Retail building
A retail building (officially named Iconic Retail) is planned to be constructed as part of the development project; it is planned to be situated across the street from the Boston Public Market and will contain four floors. The building is intended to house a flagship store, and will include an entrance to the Haymarket Square subway station.
Hotel
A 157 ft (48 m) tall hotel building is being constructed at the northern edge of the site, and is planned to contain at least 200 hotel rooms. Although the main use for the building is a hotel, at least 57 condominiums and 17,400 sq ft (1,600 m2) of retail space will be located inside the 14-story building.
Amenities
The hotel is planned to contain a ballroom, several meeting rooms, a rooftop bar, and a rooftop terrace.
Parking garage

In order to make room for the new development, the existing Government Center garage will be demolished. The garage was constructed in the 1960s as part of the Government Center urban renewal project; it contains 2,300 parking spaces. Due to the fact that the garage is entirely made out of concrete, it is considered to be an eyesore by many, along with the nearby City Hall building.[2]
At least 1,160 parking spaces in the garage are to be preserved to accommodate the new development, the spaces are planned to be placed inside of the new office tower.[9][18]