Nyagak III Power Station is a 6.6 megawatts (8,900 hp) mini hydroelectric power project, under construction in Uganda.[1]
Quick Facts Country, Location ...
Nyagak III Power Station | |
---|---|
Country | Uganda |
Location | Paidha |
Coordinates | 02°25′41″N 30°58′24″E |
Purpose | Electricity generation |
Status | Under construction |
Construction began | May 2019 |
Opening date | 2023 (Expected) |
Construction cost | US$19.4 million |
Owner(s) | Genmax Nyagak |
Operator(s) | Uganda Electricity Generation Company Limited |
Dam and spillways | |
Impounds | Nyagak River |
Reservoir | |
Normal elevation | 1,380 m (4,530 ft) |
Nyagak III Hydroelectric Power Station | |
Coordinates | 02°25′41″N 30°58′24″E |
Commission date | 2022 (Expected) |
Type | Run-of-the-river |
Turbines | 2 x 3.3 MW |
Installed capacity | (planned) 6.6 MW (8,900 hp) |
Annual generation | 36.27 GWh |