The Yuxi–Mohan railway or Yumo railway (simplified Chinese: 玉磨铁路; traditional Chinese: 玉磨鐵路; pinyin: Yùmó tiělù), is the Chinese section of the Lao–China Railway (LCR) in Yunnan Province of southwest China. The line runs 503.9 km (313 mi) from Yuxi in central Yunnan to Mohan, a town in Mengla County on the border with Laos in the Xishuangbanna Dai Autonomous Prefecture of southern Yunnan.[6] The Yumo railway is designed to "provide efficient, safe, low-carbon, affordable, railway transport" within Yunnan Province.[6]

Quick Facts Overview, Other name(s) ...
Yuxi–Mohan railway
Overview
Other name(s)Yumo railway
Native name玉磨铁路
StatusOperational
OwnerChina Railway
LocaleYunnan
Termini
Stations28
Service
Type
SystemLao–China railway
Operator(s)China Railway Kunming Group[1]
Rolling stockCR200J, HXD3C
Daily ridership19,000–33,000[2]
History
Commenced1 September 2015 (2015-09-01)[3]
Opened3 December 2021 (2021-12-03)[4]
Technical
Line length507 km (315 mi)
Number of tracks2 (north of Xishuangbanna)
1 (south of Xishuangbanna)
CharacterElevated
Track gauge1,435 mm (4 ft 8+12 in) standard gauge
Electrification25 kV 50 Hz AC overhead line
Operating speed160 kilometres per hour (99 mph) (passengers)
120 kilometres per hour (75 mph) (cargo)[5]
Route map

Yuxi
Yanhe
Qujiang bridge
Eshan
Wanhe tunnel
Luoli
Yangwu tunnel (beneath Xiaojie river)
Lixin
Ganzhuang tunnel
Yuanjiang
Nanxihe
Yuanjiang bridge
Tongda tunnel
Xiaohe bridge
Anding tunnel
Mojiang
Wanggangshan tunnel
Talanghe
Ping'an tunnel
Amojiang bridge
Xinhua tunnel
Guoyao
Dajinshan tunnel
Mohei
Ning'er
Dajianshan tunnel
Pu'er
Puwen
Mengyang tunnel
Yexianggu
Xishuangbanna tunnel
Liushahe bridge
Xishuangbanna
(Single track section below)
Feilong
Ganlanba
Manme
Suoluohe bridge
Suoluohe
Manshuishu tunnel
Guanlei
Mengyuan
Manle
Mengla tunnel
Mengla North
Mengla
Dalongha
Mohan North
Mohan
Mohan customs
Mohan tunnel,China-Laos border
Close

Branching from the existing Kunming–Yuxi–Hekou railway at Yuxi and connecting directly to the Boten–Vientiane railway on the Laotian side, the Yumo railway is a part of the Kunming–Singapore railway and will eventually carry traffic across the Greater Mekong Subregion.[6]

Yuanjiang Railway Bridge

Early stage construction began on September 1, 2015.[3] The project is estimated to cost ¥46.46 billion.[7] The railway is electrified, and has double-track from Yuxi to Jinghong and single-track from Jinghong to Mohan.[3] Cities and towns along route include Yuxi, Pu'er, Jinghong and Mohan.

The railway opened on December 3, 2021.[4]

History

After China and 17 other Asian countries signed the Trans-Asian Railway Network Agreement in June 2006, the Yuxi–Mohan railway was proposed as a component of the Kunming–Singapore railway Central Route, which would connect Kunming, Vientiane, Bangkok, Kuala Lumpur and Singapore.

In September 2010, state media in Yunnan reported that the Ministry of Railways had held a planning conference for the Yuxi–Mohan railway in August and that construction of the double track electrified line, 487.7 km (303 mi) in length and capable of accommodating trains traveling at speeds of up to 200 km/h (124 mph), would begin by the end of 2010.[8] The line was reported to cost ¥53.9 billion and take five years to build.[8] Overland travel time from Kunming to Jinghong would be reduced from 9 hours to 2.5 hours.[8]

On December 30, 2010, Chinese state media reported that early preparatory work for the Yumo railway had been completed, but the final construction plan had not been publicized.[9] Construction began on a railway logistics center in Mohan.[9][10] The railway project was delayed, however, after the removal of railway Minister Liu Zhijun for corruption in February 2011 and the subsequent reorganization of the Railway Ministry into the China Railway Corporation in March 2013.

A preliminary feasibility conference for the project was organized in Beijing on November 30, 2013 by the China Railway Corporation at which railway planners and Yunnan officials expressed their desire to see the project proceed quickly.[7]

Construction

Construction on two early-stage segments began on September 1, 2015 with the full-scale construction on the line on 19 April 2016. According to Xinhua News Agency in Yuxi, the line is scheduled to be 507.4 km long, costing 51,609 million yuan, reach maximum speeds of 160 km/h, taking 6 years to complete construction. It is scheduled to open in December 2021.[11]

Running times are scheduled to be 1.5 hours from Kunming to Eshan, to be within 3 hours from Kunming to Pu'er, to be about 3 hours from Kunming to Jinghong, and 5 hours from Kunming to Mohan.

The construction is divided into 22 segments. The 6820-meter Yueyatian Tunnel (月牙田隧道) is done on 30 December 2019.[12][13]

Stations

There are 13 stations, including:

  • Yuxi[14] (玉溪站)
  • Yanhe (研和站)
  • Eshan (峨山站)
  • Luoli (罗里站)
  • Yuanjiang (元江站)
  • Mojiang (墨江站)
  • Ning'er (宁洱站)
  • Pu'er (普洱站)
  • Mengyang (勐养站)
  • Xishuangbanna (西双版纳站) at Jinghong City - End of electrified double track section
  • Ganlanba (橄榄坝站)
  • Mengla (勐腊站)
  • Mohan (磨憨站)

Five more stations will be included later, including:

  • Feilong (飞龙)
  • Suoluohe (梭罗河)
  • Mengyuan (勐远)
  • Manle (曼勒)
  • Puwen (普文)

Rail connections

References

Wikiwand in your browser!

Seamless Wikipedia browsing. On steroids.

Every time you click a link to Wikipedia, Wiktionary or Wikiquote in your browser's search results, it will show the modern Wikiwand interface.

Wikiwand extension is a five stars, simple, with minimum permission required to keep your browsing private, safe and transparent.