Mechanical systems drawing is a type of technical drawing that shows information about heating, ventilating, air conditioning and transportation around the building (Elevators or Lifts and Escalator).[1] It is a powerful tool that helps analyze complex systems. These drawings are often a set of detailed drawings used for construction projects; it is a requirement for all HVAC work. They are based on the floor and reflected ceiling plans of the architect. After the mechanical drawings are complete, they become part of the construction drawings, which is then used to apply for a building permit. They are also used to determine the price of the project.[1]
Arrangement drawings include information about the self-contained units that make up the system: table of parts, fabrication and detail drawing, overall dimension, weight/mass, lifting points, and information needed to construct, test, lift, transport, and install the equipment. These drawings should show at least three different orthographic views and clear details of all the components and how they are assembled.[2]
The assembly drawing typically includes three orthographic views of the system: overall dimensions, weight and mass, identification of all the components, quantities of material, supply details, list of reference drawings, and notes. Assembly drawings detail how certain component parts are assembled.[2]
An assembly drawing shows which order the product is put together, showing all the parts as if they were stretched out. This will help a welder to understand how the product will go together so he get an idea of where the weld is needed. The assembly drawing will contain the following; information overall dimensions, weight and mass, identification of all the components, quantities of material, supply details, list of reference drawings, and notes.
In detail drawings, components used to build the mechanical system are described in some detail to show that the designer's specifications are met: relevant codes, standards, geometry, weight, mass, material, heat treatment requirements, surface texture, size tolerances, and geometric tolerances.[2]
A fabrication is made up of many different parts. A fabrication drawing has a list of parts that make up the fabrication. In the list, parts are identified (balloons and leader lines) and complex details are included: welding details, material standards, codes, and tolerances, and details about heat/stress treatments. and also[2]
Line diagrams and layouts indicating basic proposals, location of main items of plant, routes of main pipes, air ducts and cable runs in such detail as to illustrate the incorporation of the engineering services within the project as a whole.
The schematic is a line diagram, not necessarily to scale, that describes interconnection of components in a system. The main features of a schematic drawing show:
A drawing the intended locations of plant items and service routes in such detail as to indicate the design intent. The main features of detailed design drawings should be as follows:
A drawing which based on the detailed drawing, installation drawing or co-ordination drawing (interface drawing) with the primary purpose of defining that information needed by the tradesmen on site to install the works or concurrently work among various engineering assembly. The main features of typical installation drawings are:
A drawing showing the building and services installations as installed at the date of practical completion. Generally the record drawing is a development of the installation drawing. The main features of the record drawings should be as follows.
These drawings show the provisions required to accommodate the services that significantly affect the design of the building structure, fabric, and external works. This includes drawings (and schedules) of work the building trade carries out, or that must be cost-estimated at the design stage, e.g., plant bases
These drawings show requirements for building works necessary to facilitate installing the engineering services (other than where it is appropriate to mark out on site). Information on these drawing includes details of all:
About 80,000 jobs are held by mechanical drafters in the United States of America during 2008. From 2008 to 2018, mechanical drafting hiring rate is expected to neither increase nor decrease. It is encouraged to either take two additional years of training in drafting school after high school or attend a four-year college/university to develop better technical skills and gain more experience with CAD (computer-aided design).[3]
The American Design Drafting Association (ADDA) has developed a Drafter Certification Test. The test assesses the drafter's skill in basic drafting concepts: geometric construction, working drawings, and architectural terms and standards. The test is administered periodically at ADDA-authorized sites.[3]
Mechanical system drawings must abide by all of the following regulations: the National Building Code of Canada, the National Fire Code, and Model National Energy Code of Canada for Buildings. For residential projects, The National Housing Code of Canada and the Model National Energy Code of Canada for Houses must also be followed. These drawings must also adhere to local and provincial codes and bylaws.[1]
Seamless Wikipedia browsing. On steroids.
Every time you click a link to Wikipedia, Wiktionary or Wikiquote in your browser's search results, it will show the modern Wikiwand interface.
Wikiwand extension is a five stars, simple, with minimum permission required to keep your browsing private, safe and transparent.